Answers to the Kanban Exercise
For a system with 25 cards and essentially no WIP limits (that is, all 25 cards could be in any activity), the cycle time is 13.88 days.
For a system with WIP limits of 1 for each column, the cycle time is 2.94 days.
For a system with 25 cards and essentially no WIP limits (that is, all 25 cards could be in any activity), the cycle time is 13.88 days.
For a system with WIP limits of 1 for each column, the cycle time is 2.94 days.